AGGREGATE PLANNING AND MASTER SCHEDULING
Post: #1

AGGREGATE PLANNING AND MASTER SCHEDULING


.pdf  Aggregate Planning.pdf (Size: 163.91 KB / Downloads: 73)


INTRODUCTION
Aggregate planning is the process of planning the quantity and timing of output over the intermediate
range (often 3 to 18 months) by adjusting the production rate, employment, inventory, and other
controllable variables. Aggregate planning links long-range and short-range planning activities. It is
“aggregate” in the sense that the planning activities at this early stage are concerned with homogeneous
categories (families) such as gross volumes of products or number of customers served.
Master scheduling follows aggregate planning and expresses the overall plan in terms of the
amounts of specific end items to produce and dates to produce them. It uses information from both
forecasts and orders on hand, and it is the major control (driver) of all production activities. Figure
8.1 illustrates a simplified aggregate plan and master schedule.


VARIABLES USED IN AGGREGATE PLANNING
Aggregate planning is a complex problem largely because of the need to coordinate interacting
variables in order for the firm to respond to the (uncertain) demand in an effective way. Table 8.2
identifies some of the key variables available to planners and the costs associated with them.


AGGREGATE PLANNING STRATEGIES
Several different strategies have been employed to assist in aggregate planning. Three “pure”
strategies are recognized. The pure strategies stem from early models that depicted production
results when only one of the decision variables was permitted to vary all others being held constant.
Three focussed strategies are:
1. Vary production to match demand by changes in employment (Chase demand
strategy): This strategy permits hiring and layoff of workers, use of overtime, and subcontracting
as required in each period. However, inventory build-up is not used.
2. Produce at a constant rate and use inventories. (Level production strategy): This
strategy retains a stable work force producing at a constant output rate. Inventory can be accumulated
to satisfy peak demands. In addition, subcontracting is allowed and back orders can be accepted.
Promotional programmes may also be used to shift demand.
3. Produce with stable workforce but vary the utilization rate (Stable work-force
strategy): This strategy retains a stable work force but permits overtime, part-time, and idle time.
Some versions of this strategy permit back orders, subcontracting, and use of inventories. Although
this strategy uses overtime, it avoids the detrimental effects of layoff.



Master Scheduling Planning Horizon
The time horizon of master scheduling depends upon the type of product, volume of production, and
component lead times. It can be weeks, months, or some combination, but the schedule must normally
extend far enough into the future so that the lead times for all purchased and assembled components
are adequately encompassed.
 

Marked Categories : yhs mystartdefault, pdf aggregate planning, master of planning seminar topics, master scheduling download pdf, aggregate planning pdf, aggregate planning and usage of master schedule, aggregate planning and uses of master schedule pdf, aggregate planning uses of master scheduling, seminar in aggregate, what is aggregate planning pdf file, master scheduling, master scheduling pdf, master scheduling planning free download, functions of aggregate planning and master scheduling, agrregate planning and master scheduling, aggregate planning and master scheduling pdf, free download aggregate planning pdf, aggregate planning, aggregate planning and master scheduling,

[-]
Quick Reply
Message
Type your reply to this message here.

Image Verification
Image Verification
(case insensitive)
Please enter the text within the image on the left in to the text box below. This process is used to prevent automated posts.

Possibly Related Threads...
Thread: Author Replies: Views: Last Post
  document of key aggregate cryptosystem Guest 1 282 10-10-2017 11:31 AM
Last Post: jaseela123
  key aggregate cryptosystem ppt Guest 1 390 10-10-2017 11:30 AM
Last Post: jaseela123
  key aggregate cryptosystem ppt Guest 1 267 09-10-2017 11:52 AM
Last Post: jaseela123
  online stock trading based on scalable scheduling updates in streaming dataware house Guest 1 341 09-10-2017 10:29 AM
Last Post: jaseela123
  sleep wake scheduling ns2 code Guest 1 171 06-10-2017 03:58 PM
Last Post: jaseela123
  autocop default master password for dvr Guest 1 259 02-10-2017 03:52 PM
Last Post: jaseela123
Thumbs Down chemistry project on soybean milk and its compression milk curd and taste Guest 1 203 02-10-2017 02:38 PM
Last Post: jaseela123
  RF Controlled Robot with Metal Detector and Wireless image and voice transmission Guest 1 210 02-10-2017 12:24 PM
Last Post: jaseela123
  murach php and mysql chapter 1 quiz questions and answers pdf Guest 0 253 30-09-2017 10:18 AM
Last Post: Guest
  Investigation and Analysis of Inception Voltage and Field Distribution seminar presentation 1 7,673,584 22-09-2017 11:06 AM
Last Post: jaseela123
This Page May Contain What is AGGREGATE PLANNING AND MASTER SCHEDULING And Latest Information/News About AGGREGATE PLANNING AND MASTER SCHEDULING,If Not ...Use Search to get more info about AGGREGATE PLANNING AND MASTER SCHEDULING Or Ask Here

Options: